RICHMOND
FRIENDS MEETING
Building
Committee Request
Approved by
the
Financial
Stewardship Committee
on December 19,
2004
The Building Committee, requests that Financial Stewardship consider
and recommend to the next Meeting for Business on December 19, 2004, a $43,000
increase in the construction budget for the Religious Education Building. This increase will be used to solve two
major problems that have been encountered during the early stages of
construction. If approved, the overall
budget for the expansion and renovation of the RE Building would increase from
$590,000 to $633,000.
The first problem is the need to replace
the first floor of the Religious Education Building. When holes were dug to tie the foundation of
the addition to the existing building, the builders discovered that our
existing floor consists of only one inch of a mortar-like material over one inch
of gravel. (Apparently
they were cutting corners in 1937).
This floor should be removed and replaced with four inches of gravel and
four inches of concrete. The cost for
removal and replacement is approximately $30,000. Labor costs are high for this change order
because it is not feasible to bring large power equipment into the building to
dig up the old floor. A new floor will
solve many of the moisture problems we have experienced over the years--a
problem we would have had to address with or without this renovation.
The second problem concerns the
elevation of the outdoor meditation area and the need to prevent flooding in
the stairwell of the new side door of the multipurpose room. The builder and architect tell us the elevation
of the meditation patio needs to be raised by ten inches to ensure that water
drains away from the building. An
additional step will have to be added to the stairwell. A new retaining wall will be constructed
along with a concrete swale to drain water out to Kensington Avenue. In addition, the existing ramp for persons
with disabilities will receive a new foundation. The total cost of these changes totals
$13,000. (Note: we do wonder why these elevation and drainage issues were not
identified prior to construction. We
will address this with the architect in our next meeting.)
When we began the construction phase
of this project, we had a contingency fund of $30,000 to pay for unexpected
expenses. As one can see, the two
problems discussed above clearly exceed this amount. In addition, there are other expenses we have
incurred or expect that will be paid from the contingency fund. For example, we had to employ an independent,
engineering firm to test the steel and concrete at critical stages of
construction, and we have asbestos in our window glazing, floor tiles, and glue
that must be removed by a specialized company.
The good news is that there is no asbestos in our ceiling tiles and
glue.
There is some urgency in our deciding how best to
handle this situation. If we choose not
to increase our budget, we will have to delete something from our current
design. The only line items the Building
Committee could identify were the replacement windows on the second floor of
the RE Building, the new insulation for the north wall, and the drywall over
that insulation. Cost savings by
eliminating these items would be about $22,000.
If we choose this path, we need to inform Century Construction this
coming week so they will not order the replacement windows for the second
floor. The downside of this choice would
be our missing the opportunity to achieve new energy savings. If we replace these windows at a later time,
the costs will be more, and we would have to move out of the RE Building a
second time. We do not recommend this
course of action.
It should be noted that the Building
Committee is asking for permission to spend an additional $43,000 only if
absolutely necessary. The estimates for
the proposed work were made on the high side, and thus, we are hopeful that the
actual costs will be less. We are
looking for some cost savings during construction in the electrical area where
we may have more in the budget than actually required. There also may be more money in the budget
for furnishings than needed. Another
possibility to reduce the amount we have to borrow is to ask Building and
Grounds to spend some of our major maintenance funds to pay for part of the new
floor.
Below are the construction
and contingency budgets and along with the charges to the contingency budget to
date plus anticipated charges.
Construction
Budget $440,503
Contingency Budget $30,000
Anticipated
charges to contingency other than the floor ($30,000) and meditation area
drainage problem ($13,000)
Engineering inspections
and tests $6,000
Hardware
for one-hour fire doors 8,000
Undercut
for foundation tie-in 1,500
Asbestos
removal (floor tiles, window caulk) 5,000
Total to date $20,000
In summary, if this request is approved, we are
authorized to spend up to $43,000 to replace the first floor in the RE Building
and make the changes in the meditation area to prevent flooding. This increase will allow us to proceed with
our plans to install replacement windows, new insulation, and drywall on the
second floor of the RE Building. We will
be able to meet the contingencies we have already encountered and still have
$10,000 remaining in our contingency fund. The Building Committee recommends
the approval of this request in a timely manner to avoid delays in the
construction schedule and increased costs.
Submitted to Financial
Stewardship on December 12, 2004, on behalf of the Building Committee by Howard
Garner, Clerk of the Construction Subcommittee.